Capital improvement projects help CHWD maintain its infrastructure and keep it up to date, increase needed capacity and continue to provide great service to its customers.

TRAFFIC ALERT: Auburn Boulevard Water Main Work Expected to Cause Traffic Delays
Replacement of a 60-year-old water main along Auburn Boulevard between Cedar Drive and Linden Avenue (north of Antelope Road) in Citrus Heights is underway. Work began in mid-September 2011 and is scheduled to continue through mid-June 2012. Most of the work will take place in traffic lanes on Auburn Boulevard. Traffic control will be set up for most of the project's duration and may cause traffic delays. Motorists are advised to consider alternative routes to avoid this construction area on Auburn Boulevard.. Work on the project is scheduled to stop during the "holiday moratorium period" for construction on major thoroughfares that begins at the Thanksgiving holiday and ends after the New Years Day holiday. For more information about this project, contact Project Manager David Rossi at (916) 725-6873.


Project List
For more information on CHWD capital improvement projects, contact Project Manager David Rossi at (916) 725-6873.

Project Name
Description
Expected Start Date
Expected Completion Date
Cost
Bonita Way Storage Building Construct storage building with residential facade at Bonita Way well site. September 2010 Completed $255,000
San Juan Avenue / Madison Avenue Water Main Replacement Replace 50-year old 12-inch water main under one of the County's busiest intersections. October 2010 Completed $205,200
Auburn Blvd. Water Main Replacement Replace 60-year old 8-inch water main with new 12-inch main, from Cedar Dr. to Linden Av. September 2011 June 2012 $1.36 million
Mariposa Avenue Water Main Replacement Re-line old 12-inch and 8-inch water main from Greenback Ln. to Limerick Wy. June 2011 Completed $540,000
Livoti Av - Whyte Av - Langley Av - Frances Av Water Main Replacements Replace old water mains within streets in the project area . 2012 - Schedule to be determined 2012 - Schedule to be determined $615,000
Antelope Road Water Main Replacement Replace old 8-inch water main east from Lauppe Ln. 2012 - Schedule to be determined 2012 - Schedule to be determined $97,000



Mitchell Farms Groundwater Well
Groundwater well under construction.


What's New
     

TRAFFIC ALERT: Auburn Blvd Water Main Work Underway
FREE Irrigation Review
GREAT NEWS! No Change in Water Rates for 2012

What's New


Citrus Heights Water District  |  6230 Sylvan Road, Citrus Heights, California 95610  |  Phone: 916.725.6873 Fax: 916.725.0345
Home  |  About Us  |  Our Water  |  CHWD in the Community  |  Services  |  Customer Service  |  Water Emergencies
Operations  |  Engineering Construction  |  Contact Us